Process batches must equal move batches: True False In the Rosemount Case, Throu

ID: 379761 • Letter: P

Question

Process batches must equal move batches:                                                                           

True

False

In the Rosemount Case, Throughput was 133 units per day. What WIP level would deliver a 5 day cycle time:                                                                                                                                       

399

665

133

In the Rosemount Case, the team made arrivals to the flow lab less variable and reduced cycle time by:                                                                                                                                               

Moving meters to the flow lab more than once a day

Grouping the meters into batches by size

Reducing mean time to repair

Which of the following is true --- circle the true answers:                                                    

Scheduling is hard because of variability and complexity

Scheduling can be simplified with due date quoting

Scheduling can be simplified with sequencing in a virtual queue

As a student with knowledge of the Factory Physics Framework, I would do the following to reduce cycle time:                                                                                                                             

A Six Sigma Project

Reduce WIP

Implement advanced scheduling in an ERP planning program

In the Factory Physics Framework, the three buffers are:                                                     

Lean, Six Sigma, and ERP

Lean Six Sigma, Theory of Constraints, and Kaizens

Inventory, Time, and Capacity

What is being “buffered” in the Factory Physics Framework :                                             

Six Sigma

Business Process Reengineering

Variability

Explanation / Answer

The correct answer is FALSE. The process batch should be changeable, not fixed. A batch of full load means that the substance and time us changeable..