A manufacturing facility makes a product which consists of tasks A, , K and requ
ID: 350717 • Letter: A
Question
A manufacturing facility makes a product which consists of tasks A, , K and requires that these be completed in an order that obeys a set of precedence requirements. The following table gives the performance time in minutes/unit and the preceding task(s) for tasks A,..., K. Task Performance Time Precedin Task N/A N/A (minutes/unit) A, B D, E These tasks have been assigned to four workstations: Station 1 has tasks A and B; Station 2 has tasks C, D, and E; Station 3 has tasks F and H; and Station 4 has tasks G, I, J, and K. What is the efficiency of the line? (Specify the percentage as a two digit number after rounding. Do not include the percent sign.)Explanation / Answer
The allotment of the tasks are done as follows:
Workstation No.
1
2
3
4
Tasks
A, B
C, D, E
F, H
G, I, J, K
Total time at workstation
16
9
6
18
Thus, cycle time of the assembly line is 18 minutes (longest processing time for the workstation). The product will come out of line every 18 minutes.
Total work content or processing time for the product = 49 minutes
Efficiency = Total work content/(no. of workstation x cycle time) = 49 /(4 x 18) = 0.6805
Efficiency = 68.08%
Workstation No.
1
2
3
4
Tasks
A, B
C, D, E
F, H
G, I, J, K
Total time at workstation
16
9
6
18
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.