Question
A manufacturing facility makes a product, the manufacturing process for which consists of tasks A,. , H and requires that these be completed in an order that obeys a set of precedence requirements. The following table gives the performance time in minutes/unit and the preceding task(s) for tasks A, , H. Performance Time (minutes/unit) Preceding as Task n/a n/a A, B E, F The facility operates 7 hours/shift, 3 shifts per day, 5 days a week. If each task is assigned to its own work station, what is the throughput, i e. the number of units that can be manufactured per week? Answer: 787.5 The correct answer is: 900Explanation / Answer
Solution :
Since every task is assigned to own work station, Cycle time is equal to time for longest task.
Cycle Time = 7 min
Capacity = Total time available / Cycle Time = 7 hours * 60 minutes * 3 shifts * 5 days / 7 = 7*60*3*5/7 = 900 units
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.