If during a schedule update, the critical path changed, this can be attributed t
ID: 344518 • Letter: I
Question
If during a schedule update, the critical path changed, this can be attributed to
A change in the logic.
A change in the calendar of some activities.
A near-critical path became longer than the previous critical path.
All of the other answers.
The critical path became shorter than a near-critical path.
A change in the logic.
A change in the calendar of some activities.
A near-critical path became longer than the previous critical path.
All of the other answers.
The critical path became shorter than a near-critical path.
Explanation / Answer
All of the other answers.
The impact of the change in the critical path during a schedule update includes all the above changes owing to the basic change in the path structure that in turns affect the logic. Further, the path being critical and cannot be crushed, the calendar of some activities also witness a change with the near-critical path becoming longer than the previous one and vice versa.