Question

If during a schedule update, the critical path changed, this can be attributed to

A change in the logic.

A change in the calendar of some activities.

A near-critical path became longer than the previous critical path.

All of the other answers.

The critical path became shorter than a near-critical path.

A change in the logic.

A change in the calendar of some activities.

A near-critical path became longer than the previous critical path.

All of the other answers.

The critical path became shorter than a near-critical path.

Explanation / Answer

During the schedule update, the critical path can change if :

- The current near critical path becomes longer than the original critical path

- The current critical path becomes shorter than the near critical path

- If there is any change in logic which changes the precedence and logic

- If there is a change in the calendar and completion times of some of the activities

As all of these can be the reasons, the answer is Option D : All of the other answers