A new stamping plant must supply an automotive final assembly plant with stampin
ID: 3421775 • Letter: A
Question
A new stamping plant must supply an automotive final assembly plant with stampings, and y the number of new stamping presses must be determined. Each press will be operated by one worker. The plant will operate one 8-hour shift per day. five days per week, 50 weeks per year The plant must produce a total of 20,000,000 stampings annually. However, 400 different stamping designs are required, in batch sizes of 5000 each, so each batch will be produced 10 times per year to minimize build-up of inventory. Each stamping takes 6 sec on average to produce. Scrap rate averages 2% in this type of production. Before each batch, the press must be set up. with a standard time per setup of 3.0 hours. Presses are 95% reliable (avail-ability - 95%) during production and 100% reliable during setup. Worker efficiency is expected to be 100%. How many new stamping presses and operators will be required?Explanation / Answer
400 stamping designs will be produced 10 times each so total production batches =4000
Total hours per person per press =8*5*50=2000 hrs
Each press set up takes 3 hr so total set up time =12000 hrs
20,000,0000 stampings needed as scrap rate is 2% total stampings needed =20,000,000/.98= 20,408,164
Timefor production= 34014 hrs @ 6 sec per stamping
Total time =12000+34014= 46014
Total no of operators needed =46014/2000 = 23
No of stamping press required =400/.95 =421
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.