Using? PERT, Adam Munson was able to determine that the expected project complet

ID: 338196 • Letter: U

Question

Using? PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is

24 ?months, and the project variance is 9

?a) The probability that the project will be completed in

15

months? =

?(round your response to four decimal? places).

?b) The probability that the project will be completed in

23

months? =

?(round your response to four decimal? places).

?c) The probability that the project will be completed in

27

months? =

?(round your response to four decimal? places).

?d) The probability that the project will be completed in

33

months? =

?(round your response to four decimal? places).

?e) The due date that yields a? 95% chance of completion? =

months ?(round your response to two decimal? places).

Explanation / Answer

Using? PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is

24 ?months, and the project variance is 9

?a) The probability that the project will be completed in

15

months? =

?(round your response to four decimal? places).

?b) The probability that the project will be completed in

23

months? =

?(round your response to four decimal? places).

?c) The probability that the project will be completed in

27

months? =

?(round your response to four decimal? places).

?d) The probability that the project will be completed in

33

months? =

?(round your response to four decimal? places).

?e) The due date that yields a? 95% chance of completion? =

months ?(round your response to two decimal? places).