Activity First Week Second Week Third Week 1-2 $12 $16 $ --- 2-5 6 8 10 5-7 7 8
ID: 338095 • Letter: A
Question
Activity
First Week
Second Week
Third Week
1-2
$12
$16
$ ---
2-5
6
8
10
5-7
7
8
11
7-11
7
11
---
11-13
4
8
10
1-3
12
14
19
3-8
5
---
---
8-11
12
13
14
3-9
14
16
16
9-12
8
8
10
12-13
7
11
---
1-4
10
14
18
4-6
12
14
18
6-10
11
12
---
10-12
14
15
---
Currently the Length of the Project is
weeks.
Determine the costs to shorten the project.
1st Week Cost =
Hint: Between 2 and 6
2nd Week Cost =
3rd Week Cost =
4th Week Cost =
Hint: Between 18 and 23
Activity
First Week
Second Week
Third Week
1-2
$12
$16
$ ---
2-5
6
8
10
5-7
7
8
11
7-11
7
11
---
11-13
4
8
10
1-3
12
14
19
3-8
5
---
---
8-11
12
13
14
3-9
14
16
16
9-12
8
8
10
12-13
7
11
---
1-4
10
14
18
4-6
12
14
18
6-10
11
12
---
10-12
14
15
---
Explanation / Answer
Activity
First Week
Second Week
Third Week
1-2
$12
$16
$ ---
2-5
6
8
10
5-7
7
8
11
7-11
7
11
---
11-13
4
8
10
1-3
12
14
19
3-8
5
---
---
8-11
12
13
14
3-9
14
16
16
9-12
8
8
10
12-13
7
11
---
1-4
10
14
18
4-6
12
14
18
6-10
11
12
---
10-12
14
15
---
Currently the Length of the Project is
weeks.
Determine the costs to shorten the project.
1st Week Cost =
Hint: Between 2 and 6
2nd Week Cost =
3rd Week Cost =
4th Week Cost =
Hint: Between 18 and 23
Activity
First Week
Second Week
Third Week
1-2
$12
$16
$ ---
2-5
6
8
10
5-7
7
8
11
7-11
7
11
---
11-13
4
8
10
1-3
12
14
19
3-8
5
---
---
8-11
12
13
14
3-9
14
16
16
9-12
8
8
10
12-13
7
11
---
1-4
10
14
18
4-6
12
14
18
6-10
11
12
---
10-12
14
15
---
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.