Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Activity First Week Second Week Third Week 1-2 $12 $16 $ --- 2-5 6 8 10 5-7 7 8

ID: 450929 • Letter: A

Question

Activity

First Week

Second Week

Third Week

1-2

$12

$16

$ ---

2-5

6

8

10

5-7

7

8

11

7-11

7

11

---

11-13

4

8

10

1-3

12

14

19

3-8

5

---

---

8-11

12

13

14

3-9

14

16

16

9-12

8

8

10

12-13

7

11

---

1-4

10

14

18

4-6

12

14

18

6-10

11

12

---

10-12

14

15

---





The Current Length of the Project is

weeks.


Determine the costs to shorten the project.


1st Week Cost =

Hint: Between 2 and 7
2nd Week Cost =


3rd Week Cost =


4th Week Cost =

Hint: Between 15 and 21


Note: For each week you are to include only the cost of shortening the activities in that particular week

Activity

First Week

Second Week

Third Week

1-2

$12

$16

$ ---

2-5

6

8

10

5-7

7

8

11

7-11

7

11

---

11-13

4

8

10

1-3

12

14

19

3-8

5

---

---

8-11

12

13

14

3-9

14

16

16

9-12

8

8

10

12-13

7

11

---

1-4

10

14

18

4-6

12

14

18

6-10

11

12

---

10-12

14

15

---

Explanation / Answer

a. There is some missing portion in the question or might be image was not loading for my connection. Therefore, I could not find out length of time for normal activities also PERT diargram was missing from question and hence can not find out length of project

From PERT diagram one has to understand critical path and then sum all the time length to come at length of project.

b. Cost to shorten the project

First week cost

Consider that table given in question is critical path then , cost is sum of all cost to shorten project by one week which is $141

2nd week cost - Applying same logic - $168

3rd week cost - Applying same logic - $126

Activity First Week Second Week Third Week 1--2 $12 $16 $ --- 2--5 6 8 10 5--7 7 8 11 7--11 7 11 --- 11--13 4 8 10 1--3 12 14 19 3--8 5 --- --- 8--11 12 13 14 3--9 14 16 16 9--12 8 8 10 12--13 7 11 --- 1--4 10 14 18 4--6 12 14 18 6--10 11 12 --- 10--12 14 15 ---
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote