Two mutually exclusive projects have cash flows as shown below. What is the IRR
ID: 2752975 • Letter: T
Question
Two mutually exclusive projects have cash flows as shown below. What is the IRR of each project? Based on information given so far, can you give a recommendation, which project to accept? Please explain. When would you accept project 1 - at lower or higher discount rates? Explain When would you accept project 2 - at lower or higher discount rates? Explain At what discount rate would you be indifferent between the two projects? What is this point called on a diagram? What is the IRR of each project? Based on information given so far, can you give a recommendation, which project to accept? Please explain. When would you accept project 1 - at lower or higher discount rates? Explain When would you accept project 2 - at lower or higher discount rates? Explain At what discount rate would you be indifferent between the two projects? What is this point called on a diagramExplanation / Answer
Answer-b
Project-2 Scores high on IRR as its IRR = 43.54% is well above the IRR of Project-1 which is 23.38%.
So as per the IRR criteria Project-2 is acceptable.
Answer-c
We can accept projects at discount rate lower than the IRR only. As in that case only we can have positive NPV.
Answer-d
We can accept projects at discount rate lower than the IRR only. As in that case only we can have positive NPV.
Answer-e
We have to find out the differential cash flows of Project-1 and 2 and then IRR of those cash flows to get that discount rate at which we would be indifferent between the projects.
So the indifference rate = 15.38%
This point on the graph is known as indifference point.
Year Project -1 Project -2 Difference between P-1 and P-2 0 -100 -40 -60 1 50 40 10 2 50 25 25 3 50 50 IRR = 15.38%Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.