Two mutually exclusive projects are under consideration. Year Project A Project
ID: 1180506 • Letter: T
Question
Two mutually exclusive projects are under consideration.
Year Project A Project B
0 -$5,000 -$9,000
1 $2,750 $1,000
2 $2,750 $3,000
3 $2,750 $5,000
4 $2,750 $7,000
5 $2,750 $9,000
(a) Which project should be selected if the simple payback method is used to make the
determination?
(b) Which project should be selected if NPW or NFW were used? Consider the time value
of money to be 15%.
(c) Explain any differences in results.
Explanation / Answer
a) If the simple payback method is used, Project A is selected.
b) if NPV is used, Project B is used as Project B's net present value is higher than Project A's NPV
c) The difference is due to the time value of money where a future dollar is worth less than a dollar today. By discounting cash flows in the future, Project B is better on a present value basis.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.