Question
The WBS which is the big part of project Scope is designed to provide different information for decision making. For example, this database provides information for the following types of decisions: a. Link deliverables, organization units, and customer b. Provide for control c. Isolate problems to source d. Track schedule and cost variance. Network does not.... e. Assign responsibility and budgets f. Focus attention on deliverables g. Provide information for different levels in the organization
Question: How does the WBS differ from the project network? How are WBS and project networks linked? Please share examples
Explanation / Answer
Many project managers get confused between work breakdown structure and project network.so,often they schedule and breakdown the project in one step.But these two things are different from each other.The main difference between WBS and project network are:
Though the project network and WBS are different from each other ,still they are closely linked with one another.Projects network and WBS both are the parts of a project plan.WBS refers to a managable division of work to accomplish the project objectives and creat the required deliverables.A project network is a graphic flowchart of a project plan that is developed from the Work Breakdown Structure(WBS).A project network is developed to identify and document dependencies among scheduled activities that have been identified in the WBS.It is mainly useful to identify the critical path and understand how best to sequence the activities of the project.Once the work breakdown is done one can estimate the time for completion of the activities and make project schedule applicable.
For example, if a building is constructed foundation and roofing can be WBS.but the plastering and brickworks put together called project network.