A project has four activities (A, B, C, and D) that must be performed sequential

ID: 2745562 • Letter: A

Question

A project has four activities (A, B, C, and D) that must be performed sequentially. The probability distributions for the time required to complete each of the activities are as follows:

A. Provide the base-case, worst-case, and best-case calculations for the time to complete the project.


B. Use the random numbers 0.8634, 0.8928, 0.7531 and 0.7648 to simulate the completion time of the project in weeks.


Activity Activity Time
(weeks)

Probability A 3 0.30 4 0.33 5 0.26 6 0.11 B 7 0.19 9 0.55 11 0.26 C 15 0.10 17 0.22 19 0.44 21 0.20 23 0.04 D 8 0.66 10 0.34

Explanation / Answer

In Base case scenario, time with highest probability is considered.

In Worst case scenario, highest time of completion is considered

In Best case, the lowest time of completion is considered.

Activity

Base case

Worst case

Best case

A

4 weeks

6 weeks

3 weeks

B

9 weeks

11 weeks

7 weeks

C

19 weeks

23 weeks

15 weeks

D

8 weeks

10 weeks

8 weeks

Activity Time

Cumulative

Random Number interval

Activity

(weeks)

Probability

A

3

0.30

0.30

0.00 but less than 0.30

4

0.33

0.63

0.30 but less than 0.63

5

0.26

0.89

0.63 but less than 0.89

6

0.11

1.00

0.89 but less than 1.00

Activity Time

Cumulative

Random Number interval

Activity

(weeks)

Probability

B

7

0.19

0.19

0.00 but less than 0.19

9

0.55

0.74

0.19 but less than 0.74

11

0.26

1.00

0.74 but less than 1.00

Activity

(weeks)

Probability

Cumulative

Random Number interval

C

15

0.10

0.10

0.00 but less than 0.10

17

0.22

0.32

0.10 but less than 0.32

19

0.44

0.76

0.32 but less than 0.76

21

0.20

0.96

0.76 but less than 0.96

23

0.04

1.00

0.96 but less than 1.00

Activity Time

Cumulative

Random Number interval

Activity

(weeks)

Probability

D

8

0.66

0.66

0.00 but less than 0.66

10

0.44

1.0

0.66 but less than 1.00

Activity

Random Number

Completion Time

A

0.8634

5 weeks

B

0.8928

11 weeks

C

0.7531

11 weeks

D

0.7648

10 weeks

Activity

Base case

Worst case

Best case

A

4 weeks

6 weeks

3 weeks

B

9 weeks

11 weeks

7 weeks

C

19 weeks

23 weeks

15 weeks

D

8 weeks

10 weeks

8 weeks