5) Given the critical path below, calculate the following a. The crash cost per

ID: 2698619 • Letter: 5

Question

5) Given the critical path below, calculate the following

a. The crash cost per unit time savings for each activity.

b. The maximum total crash time savings and cost.

c. The maximum total time-savings with a $3000 budget.

Activity

Normal Time

Normal Cost

Crash Duration

Crash Cost

A

8 days

$8,000

7 days

$12,000

B

5 days

$2,000

3 days

$10,000

C

10 days

$9,000

9 days

$12,000

Activity

Normal Time

Normal Cost

Crash Duration

Crash Cost

A

8 days

$8,000

7 days

$12,000

B

5 days

$2,000

3 days

$10,000

C

10 days

$9,000

9 days

$12,000

Explanation / Answer

a)cost crash per period=cc-nc/nt-ct

activity cost crash

A 4000

B 4000

C 3000


b)The maximum total crash time savings and cost.

NT-CT

activity NT-CT

A 1

B 2

C 1