Dog Up! Franks is looking at a new sausage system with an installed cost of $490
ID: 2696798 • Letter: D
Question
Dog Up! Franks is looking at a new sausage system with an installed cost of $490,000. This cost will be depreciated straight-line to zero over the projects five-year life, at the end of which the sausage system can be scrapped for $72,000. The sausage system will save the firm $170,000 per year in pretax operating costs, and the system requires an initial investment in net working capital of $31,000. If the tax rate is 30 percent and the discount rate is 8 percent, what is the NPV of this project?
Explanation / Answer
I = 490000+31000 = 521000
depreciation per yr = 490000/5 = 98000
terminal cost = 72000
cash flow yr 1 = 170000-.3*(170000-98000) = $148400
fr yr 2, 3,4 is same
fr yr 5 = 148400+72000 = $220400
NPV = $120,520.8
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.