Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Cummings Products Company is considering two mutually exclusive investments whos

ID: 2640252 • Letter: C

Question

Cummings Products Company is considering two mutually exclusive investments whose expected net cash flows are as follows:

Construct NPV profiles for Projects A and B.

Select the correct graph.

The correct graph is -Select-ABCDItem 1 .

What is each project's IRR? Round your answers to two decimal places.

Project A %

Project B %

Calculate the two projects' NPVs, if you were told that each project's cost of capital was 10%. Round your answers to the nearest cent.

Project A    $  

Project B    $  

Which project, if either, should be selected?
-Select-Project AProject BItem 6

Calculate the two projects' NPVs, if the cost of capital was 17%. Round your answers to the nearest cent.

Project A    $  

Project B    $  

What would be the proper choice?
-Select-Project AProject BItem 9

What is each project's MIRR at a cost of capital of 10%? (Hint: Note that B is a 6-year project.) Round your answers to two decimal places.

Project A %

Project B %

What is each project's MIRR at a cost of capital of 17%? (Hint: Note that B is a 6-year project.) Round your answer to two decimal places.

Project A %

Project B %

What is the crossover rate? Round your answer to two decimal places.
%

EXPECTED NET CASH FLOWS Year Project A Project B 0 -$300 -$405 1 -387 134 2 -193 134 3 -100 134 4 600 134 5 600 134 6 850 134 7 -180 134 Cummings Products Company is considering two mutually exclusive investments whose expected net cash flows are as follows: Construct NPV profiles for Projects A and B. Select the correct graph. The correct graph is -Select-ABCDItem 1 . What is each project's IRR? Round your answers to two decimal places. Project A % Project B % Calculate the two projects' NPVs, if you were told that each project's cost of capital was 10%. Round your answers to the nearest cent. Project A $ Project B $ Which project, if either, should be selected? -Select-Project AProject BItem 6 Calculate the two projects' NPVs, if the cost of capital was 17%. Round your answers to the nearest cent. Project A $ Project B $ What would be the proper choice? -Select-Project AProject BItem 9 What is each project's MIRR at a cost of capital of 10%? (Hint: Note that B is a 6-year project.) Round your answers to two decimal places. Project A % Project B % What is each project's MIRR at a cost of capital of 17%? (Hint: Note that B is a 6-year project.) Round your answer to two decimal places. Project A % Project B % What is the crossover rate? Round your answer to two decimal places. %

Explanation / Answer

Part (a) - Which graph is correct

NPV is acronym for Net Present Value, which means the difference in present values of the outflow and present values of the inflow in a project or decision making involving flow and receipt of funds.

In the given scenario NPV of both the project at cost of capital at 0% are:

Table showing net cash flows of both the projects at Cost of Capital at 0%

Year

Project A

Project B

0

$       (300)

$       (405)

1

$       (387)

$         134

2

$       (193)

$         134

3

$       (100)

$         134

4

$         600

$         134

5

$         600

$         134

6

$         850

$         134

7

$       (180)

$         134

NPV

$         890

$         533

Solution : Taking above table as the basis graph D is right

Part (b)

IRR is acronym for Internal Rate of Return, which means that at what discount rate NPV of a project or decision making involving flow and receipt of funds will be zero.

In the given scenario NPV as zero of both the projects lies between 15% - 20% for Project A and 25% - 30% for project B as shown in the table:

Table showing net cash flows of both the projects at various discount rates

For Project A                                                                            

Year

PV at 0% (in $)

PV at 15% ($)

PV at 20% ($)

0

-300

-300

-300

1

-387

-336.52

-322.50

2

-193

-145.94

-134.03

3

-100

-65.75

-57.87

4

600

343.05

289.35

5

600

298.31

241.13

6

850

367.48

284.66

7

-180

-67.67

-50.23

NPV

890

92.96

-49.49

For Project B

Year

PV at 0% ($)

PV at 25% ($)

PV at 30% ($)

0

-405

-405

-405

1

134

107.20

103.08

2

134

85.76

79.29

3

134

68.61

60.99

4

134

54.89

46.92

5

134

43.91

36.09

6

134

35.13

27.76

7

134

28.10

21.36

NPV

533

18.59

-29.52

Using this formula we drive the IRR of the Projects = Lowest discount rate from the table for each project + (Difference in the discount rates

Year

Project A

Project B

0

$       (300)

$       (405)

1

$       (387)

$         134

2

$       (193)

$         134

3

$       (100)

$         134

4

$         600

$         134

5

$         600

$         134

6

$         850

$         134

7

$       (180)

$         134

NPV

$         890

$         533

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote