Question
Final Exam Torhr Layout References Mailings Review View Help Tell me what you want to do into the word document (do not provide your project management tiles) What is precision medicine? How is precision medicine different from predictive medicine? (10 points) 6. Given the following information and formulae from the lecture, calculate earned value and cost variance (10 points): 7. Rate of performance: 65% Planned value: $4000 Actual cost: $6000 a Using the data in the table, and provided severity of CHF, Mi, Diabetes, Hypertension alcohol use, assess the overall severity of the nine cases in Table below. Plot the patient s length of stay against overall severity of ilness (40 points)Explanation / Answer
Cost varaince is used to measure the variance between actual cost and budget cost.Cost variance is one of the measure for performance of the project.Cost Variance can be calculated by Earned Value-Actual Cost
Earned Value is used as a projection or by using a status of completion ie. how much budget is required and how much time is required considering the amount of work donr till day.
Planned Value is the budgeted amount through the current reporting period
Actual Cost=Actula Cost to date
Earned Value=TOtal budget of the Project*% completion of the project
GIven Performance=65%
Planned Value=$4000
Actual Cost=$6000
Earned Value=$4000*65%=$2600
Cost of Variance=Earned Value-Actual Cost
=$2600-$6000=$3400
Hence the budget is underbudgeted.The actual cost is more than the Earned Value and the budget is to be revised