A project is accepted under the net present value method when

the net present value is zero or negative.

the purchase price of the asset is less than the present value of net cash inflows.

the total amount of cash inflows exceeds the purchase price of the asset.

the present value of net cash inflows exceeds a predetermined minimum amount.

A.

the net present value is zero or negative.

B.

the purchase price of the asset is less than the present value of net cash inflows.

C.

the total amount of cash inflows exceeds the purchase price of the asset.

D.

the present value of net cash inflows exceeds a predetermined minimum amount.

Explanation / Answer

As per the question and A, B, C, D options given a project can be accepted when (C) the total amount of cash inflows exceeds the purchase price of the asset