DM & DL variances Aquatica uses a standard cost system for materials and labor i

ID: 2446176 • Letter: D

Question

DM & DL variances

Aquatica uses a standard cost system for materials and labor in producing small fishing boats. Production requires three materials: fiberglass, paint, and a purchased trim package. The standard costs and quantities for materials and labor are as follows:

The following actual data related to the production of 600 boats was recorded for July:

Calculate the material and labor variances for Aquatica for July. The material price variance should be computed for each type of material and on the quantity of material purchased:

Fiberglass Price Variance:

Fiberglass Quantity Variance:

Paint Price Variance:

Paint Quantity Variance:

Trim Price Variance:

Trim Quantity Variance:

Labor Rate Variance:

Labor Efficiency Variance:

Total Labor Variance:

Explanation / Answer

Fibreglass Price Variance= Actual Cost-Standard Cost

=(21,00,000*$1.83)- (21,00,000*1.80)

= 63,000

Fibreglass Quantity Variance= (Actual Material Used-Standard Material Requirement)*Standard Price

= (13,80,000/600)-2000*($1.80)

=(2300-2000)*1.8

=54,000

Paint price variance = Actual Cost-Standard cost for Actual Purchase

=(1000*$55.50)-(1000*60)

= 55,500-60,000

= (4500)

Note: 4 Quart= 1Gallon

Paint Quantity Variance= Actual Quantity-Standard Quantity

=1000-(600*6/4)*60

= (1000-900)*60

= 60,000

Trim Price Variance= Actual Price-Standard Price for Actual Purchase

= (640*$205)-(640*$200)

= 1,31,200-1,28,000

=3200

Trim Qiuantity Variance= Actual Consumption at Standard price-Standard Consumption at standard price

=(608*$200)-(600*$200)

= 1,21,600-1,20,000

=1600

Labour Rate Variance= (Actual Rate-Standard Rate)*Actual labour used

=($23.5-$25)*23850

=-$1.5*23850

=-35,775

Labour Efficiency Variance= Actual hours*Standard rate-Standard hours*standard rate

=23850*25-24000*25

=-3750

Total Labour Variance = Actual cost-budgeted cost for actual production

=(23850*23.5)-(24000*25)

=560475-6,00,000

=-39525