Burte Corporation prepared the following variance report. Fill in the missing am
ID: 2427835 • Letter: B
Question
Burte Corporation prepared the following variance report.
Fill in the missing amounts or letters in the report. (Round price to 2 decimal places, e.g. 2.75.)
BURTE CORPORATION
Variance Report—Purchasing Department
For Week Ended January 9, 2014
Type of
Materials
Quantity
Purchased
Actual
Price
Standard
Price
Price
Variance
Explanation
BURTE CORPORATION
Variance Report—Purchasing Department
For Week Ended January 9, 2014
Type of
Materials
Quantity
Purchased
Actual
Price
Standard
Price
Price
Variance
Explanation
Explanation / Answer
price variance=(standard cost- Actual cost incurred)* actual quantity of units prchased
For Rouge11
5244=(5.17-4.98)*quantity purchased
Quantity purchased=27600 lbs.
For Storm17
912=(actual price-3.26)*5700
Actual price= $3.42
Beast29
800=(0.39- standard price)*20000
standard price= $0.35
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.