Please help me answer this questions Evener Inc. has provided the following data
ID: 2421789 • Letter: P
Question
Please help me answer this questions
Evener Inc. has provided the following data for the month of July. There were no beginning inventories; consequently, the direct materials, direct labor, and manufacturing overhead applied listed below are all for the current month. Manufacturing overhead for the month was overapplied by $3,000. The company allocates any underapplied or overapplied overhead among work in process, finished goods, and cost of goods sold at the end of the month on the basis of the overhead applied during the month in those accounts. Determine the cost of work in process, finished goods, and cost of goods sold AFTER allocation of the underapplied or overapplied overhead for the period.Explanation / Answer
Manufacturing Overhead for the month is overapplied by $3000
WIP = 14750-(4950/33000x3000) = 14750-450 =14300
Finished Goods = 44670-(11550/33000x3000) = 44670-1050 = 43620
COGS = 63300-(16500/33000x3000) = 63300-1500 = 61800
Cost of WIP, Finished goodsand COGS after allocation of opplied MAnufacturing overhesd = 14300+43620+61800
=$ 119720
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.