An incomplete subsidiary ledger of materials inventory for May is as follows: a.

ID: 2399933 • Letter: A

Question

An incomplete subsidiary ledger of materials inventory for May is as follows:

a. Complete the materials issuances and balances for the materials subsidiary ledger under FIFO.

b. Determine the materials inventory balance at the end of May.
$

c. Journalize the summary entry to transfer materials to work in process.

Received Issued Balance Receiving
Report
Number
Quantity Unit
Price
Materials
Requisition
Number
Quantity Amount Date Quantity Unit
price
Amount May 1 370 $6 $2,220 27 260 $8 May 4 100 420 $ May 10 33 170 10 May 21 113 250 May 27

Explanation / Answer

Answers

Received

Issued

Balance

Receiving

Quantity

Unit

Materials

Quantity

Amount

Date

Quantity

Unit

Amount

Report

Price

Requisition

price

Number

Number

[A]

[B]

[A x B]

[C]

[D]

[E]

[F]

[E x F]

May-01

370

$                   6.00

$       2,220.00

27

260

$                          8.00

$                       2,080.00

May-04

370

$                   6.00

$       2,220.00

260

$                   8.00

$       2,080.00

100

420

$          2,620.00 [(370 x 6) + (50 x 8)]

May-10

210

$                   8.00

$       1,680.00

33

170

$                       10.00

$                       1,700.00

May-21

210

$                   8.00

$       1,680.00

170

$                10.00

$       1,700.00

113

250

$          2,080.00 [(210 x 8) + (40 x 10)

May-27

130

$            10.00

$       1,300.00

Material Inventory at the end = 130 units at $ 10 = $ 1,300.00

Amount = 420 units at $ 2,620 + 250 units at $ 2,080 = 2620 + 2080 = $ 4,700


Work in Process

$ 4,700

Materials

$ 4,700

Received

Issued

Balance

Receiving

Quantity

Unit

Materials

Quantity

Amount

Date

Quantity

Unit

Amount

Report

Price

Requisition

price

Number

Number

[A]

[B]

[A x B]

[C]

[D]

[E]

[F]

[E x F]

May-01

370

$                   6.00

$       2,220.00

27

260

$                          8.00

$                       2,080.00

May-04

370

$                   6.00

$       2,220.00

260

$                   8.00

$       2,080.00

100

420

$          2,620.00 [(370 x 6) + (50 x 8)]

May-10

210

$                   8.00

$       1,680.00

33

170

$                       10.00

$                       1,700.00

May-21

210

$                   8.00

$       1,680.00

170

$                10.00

$       1,700.00

113

250

$          2,080.00 [(210 x 8) + (40 x 10)

May-27

130

$            10.00

$       1,300.00