9) Villanova, Inc., has done a cost analysis for its production of rubber stamps
ID: 2340890 • Letter: 9
Question
9)
Villanova, Inc., has done a cost analysis for its production of rubber stamps. The following activities and cost drivers have been developed:
Activity Cost Formula
Design $5,000 + $0.05 per machine hour
Machining $25,000 + $0.01 per machine hour
Setups $35 per batch
Purchasing $50 + $15 per purchase order
Following are the actual costs of producing 35,000 rubber stamps: 1,000 machine hours; 5 batches; 30 purchase orders
Design
$5,080
Machining
?
Setups
?
Purchasing
$600
The following variances were given in the activity performance report:
Design
?
Machining
$40 F
Setups
$15 F
Purchasing
?
What is the activity variance for purchasing?
(0.5pts)
$500 U
$100 U
$50 U
none of these
Explanation / Answer
Ans. The Activity Variance for Purchasing = $100 U
Actual Purchasing = $600
Less:- Budgeted Purchasing = $50 +( $15 per Purchase order x 30 purchases order ) =$500
Activity Variance = $100 U