Wayne County will build an aqueduct to bring water in from the upper part of the state. It can be built at a reduced size now for $300 million and be enlarged 25 years hence for an additional $350 million. An alternative is to construct the full - s ized aqueduct now for $400 million. Both alternatives would provide the needed capacity for the 50 - year analysis period. Maintenance costs are small and may be ignored. At 6% interest, which alternative should be selected?

a.Do nothing

b.Two Stage Construction (reduced)

c.One Stage Construction (full)

Explanation / Answer

For two stage construction:

PW of cost = $300 million + $350 million (P/F,6%,25) = $350 million + $81.6 million = $381.6 million

For single stage construction:

PW of cos = $400 million

As present worth of cost of second stage construction is low hence it is more preferrable.

Option b is correct.