A landscaping company is considering renting a backhoe at $12,000 for the season. The variable cost of completing a landscaping project with the use of the backhoe is $500. Alternatively, without the use of the backhoe, the company would incur a variable cost of $1,000 per landscaping project and no fixed costs. If the landscaping company plans to complete more than _____ projects, the total cost of landscaping projects will be lower _____. 12; without the backhoe 44; without the backhoe 24; with the backhoe 18; with the backhoe A landscaping company is considering renting a backhoe at $12,000 for the season. The variable cost of completing a landscaping project with the use of the backhoe is $500. Alternatively, without the use of the backhoe, the company would incur a variable cost of $1,000 per landscaping project and no fixed costs. If the landscaping company plans to complete more than _____ projects, the total cost of landscaping projects will be lower _____. 12; without the backhoe 44; without the backhoe 24; with the backhoe 18; with the backhoeExplanation / Answer
Answer
option
24; with the backhoe
total cost =fixed cost +variable cost
variable cost=cost per project*number of project
TC without the backhoe
for 12 projects
=12*1000=12000
for 24 projects
=24*1000=24000
for 44 projects
=44*1000=44000
with the backhoe
for 12 projects
=12*500+12000=18000
for 24 projects
=24*500+12000=24000
for 44 projects
=44*500+12000=34000
for 24 projects the cost is same and above it decreases with the backhoe
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.