1.It is well known that team crew size has an impact on labor productivity. A ma
ID: 470632 • Letter: 1
Question
1.It is well known that team crew size has an impact on labor productivity. A manager of a carpet store is trying to determine the best installation crew size. He tried various team sizes with the results shown below. Based on productivity, what crew size will you recommend?
Crew Size
Hours of work
Yards Installed
2
2 hours
1659
3
3 hours
3900
4
2 hours
3120
5
1 hour
2290
2.
The manager of a new carpet store is hiring. The data showed that on average a worker can install 271 yards per hour (capacity). Considering providing reasonable breaks the manager hired 18 workers to make sure they can complete 20,000 yards each 8 hours day. What is the labor utilization? Just fill in the number, no unit, no formula, no explanation, and no %. Keep two decimal points. For example, if your answer is 56%, fill in as 0.56. Do the rounding only at the last step to make sure your number is accurate enough.
Crew Size
Hours of work
Yards Installed
2
2 hours
1659
3
3 hours
3900
4
2 hours
3120
5
1 hour
2290
Explanation / Answer
1) Productivity = Output per period/ No of hours employees at work
=1659/4 = 414.75 installs per hour
The crew size 5 has the higher productivity then the remaining crew size. So i recommend crew size 5
2) labor utilization = (Actual output/ capacity)100
Actual output = 20,000
worker can install 271 yards per hour
Per 8 hours = 271 * 8 = 2168 yards
Total labor Capacity = 18*2168 = 39024 yards
labor utilization = (20,000/39024)*100 = 51.25%
Crew size hours of work yards installed Productivity 2 2 1659=1659/4 = 414.75 installs per hour
3 3 3900 =3900/9 = 433.33 installs per hour 4 2 3120 =3120/8 = 390.00 installs per hour 5 1 2290 =2290/5 = 458.00 installs per hourRelated Questions