1.It is well known that team crew size has an impact on labor productivity. A ma

ID: 470632 • Letter: 1

Question

1.It is well known that team crew size has an impact on labor productivity. A manager of a carpet store is trying to determine the best installation crew size. He tried various team sizes with the results shown below. Based on productivity, what crew size will you recommend?

Crew Size

Hours of work

Yards Installed

2

2 hours

1659

3

3 hours

3900

4

2 hours

3120

5

1 hour

2290

2.

The manager of a new carpet store is hiring. The data showed that on average a worker can install 271 yards per hour (capacity). Considering providing reasonable breaks the manager hired 18 workers to make sure they can complete 20,000 yards each 8 hours day. What is the labor utilization? Just fill in the number, no unit, no formula, no explanation, and no %. Keep two decimal points. For example, if your answer is 56%, fill in as 0.56. Do the rounding only at the last step to make sure your number is accurate enough.

Crew Size

Hours of work

Yards Installed

2

2 hours

1659

3

3 hours

3900

4

2 hours

3120

5

1 hour

2290

Explanation / Answer

1) Productivity = Output per period/ No of hours employees at work

=1659/4 = 414.75 installs per hour

The crew size 5 has the higher productivity then the remaining crew size. So i recommend crew size 5

2) labor utilization = (Actual output/ capacity)100

Actual output = 20,000

worker can install 271 yards per hour

Per 8 hours = 271 * 8 = 2168 yards

Total labor Capacity = 18*2168 = 39024 yards

labor utilization = (20,000/39024)*100 = 51.25%

Crew size hours of work yards installed Productivity 2 2 1659

=1659/4 = 414.75 installs per hour

3 3 3900 =3900/9 = 433.33 installs per hour 4 2 3120 =3120/8 = 390.00 installs per hour 5 1 2290 =2290/5 = 458.00 installs per hour