Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount
ID: 468941 • Letter: M
Question
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:
1. Compute the throughput time. (Round your answer to 1 decimal place.)
2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your answer to the nearest whole percentage (i.e., 0.12 should be entered as 12).)
What percentage of the throughput time was spent in non–value-added activities? (Round your answer to the nearest whole percentage (i.e., 0.12 should be entered as 12).)
Compute the delivery cycle time. (Round your intermediate calculations and final answer to 1 decimal place.)
If by using Lean Production all queue time during production is eliminated, what will be the new MCE? (Do not round intermediate calculations. Round your answer to the nearest whole percentage (i.e., 0.12 should be entered as 12).)
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:
Inspection time 0.7 days Wait time (from order to start of production) 16.6 days Process time 2.7 days Move time 1.3 days Queue time 4.5 days Required:1. Compute the throughput time. (Round your answer to 1 decimal place.)
2. Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your answer to the nearest whole percentage (i.e., 0.12 should be entered as 12).)
3.What percentage of the throughput time was spent in non–value-added activities? (Round your answer to the nearest whole percentage (i.e., 0.12 should be entered as 12).)
4.Compute the delivery cycle time. (Round your intermediate calculations and final answer to 1 decimal place.)
5.If by using Lean Production all queue time during production is eliminated, what will be the new MCE? (Do not round intermediate calculations. Round your answer to the nearest whole percentage (i.e., 0.12 should be entered as 12).)
Explanation / Answer
1. Throughput Time = Process time + Inspection Time + Move Time + Queue Time
Throughput Time = 2.7 days + 0.7 days + 1.3 days + 4.5 days = 9.2 days
2. Value Added Time = Process Time = 2.7 days
MCE = Value Added Time / Throughput Time = 2.7 / 9.2 = 0.2935 = 29.35 %
3. Percentage of the throughput time was spent in non–value-added activities = 100 - 29.35 = 70.65%
4. Delivery Cycle time = wait Time + Throughput Time = 16.6 + 9.2 = 25.8 days
5. New Throughput Time = Process time + Inspection Time + Move Time = 2.7 + 1.3 + 0.7 = 4.7 days
New MCE = Value Added Time / New Throughput Time = 2.7 / 4.7 = 0.5745 = 57.45%
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.