Department S had no work in process at the beginning of the period. 11,361 units
ID: 468224 • Letter: D
Question
Department S had no work in process at the beginning of the period. 11,361 units of direct materials were added during the period at a cost of $79,527, 8,521 units were completed during the period, and 2,840 units were 38% completed as to labor and overhead at the end of the period. All materials are added at the beginning of the process. Direct labor was $51,938 and factory overhead was $8,329. What were the total cost of units completed during the period? Select the correct answer. $113,139
$79,527
$26,655
$139,794
Explanation / Answer
Data Given:
Units added during the start of period = 11,361 units
Total materials cost = $79,527
Units completed during the period = 8,521 units
Work in process units during period = 2840 units
Completed work on work in process = 38%
Direct Labor = $51,938
Factory Overhead = $8,329
To determine total cost of units completed first determine unit material cost, unit labor cost, and unit overhead cost.
Determining Unit Material cost (CM):
CM = (material cost)/(Units added)
CM = $79,527/11,361
CM = $7
Determining Unit Labor cost (CM):
Direct Labor = unit labor cost x (units completed + units in process x % complete)
$51,938 = CM (8,521 + 0.38 x 2,840)
$51,938 = CM (8,521 + 0.38 x 2,840)
$51,938 = CM x 9600.2
CM = $5.41
Determining Unit factory overhead cost (CO):
Direct overhead cost = unit overhead cost x (units completed + units in process x % complete)
$8,329 = CO (8,521 + 0.38 x 2,840)
$8,329 = CO (8,521 + 0.38 x 2,840)
$8,329 = CO x 9600.2
CM = $0.87
The total unit cost of a completed unit is $7 materials + $5.41 labor + $0.87 overheads = $13.27 per unit.
Total cost of completed units = completed units x total unit cost
Total cost of completed units = 8,521 units x $13.27 per unit.
Total cost of completed units = 113158.88
Correct Option is: $113,139
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.