Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

United Research Associates (URA) had received a contract to produce two units of

ID: 466356 • Letter: U

Question

United Research Associates (URA) had received a contract to produce two units of a new cruise missile guidance control. The first unit took 5,000 hours to complete and cost $30,000 in materials and equipment usage. The second took 3,750 hours and cost $19,500 in materials and equipment usage. Labor cost is charged at $25 per hour.

     The prime contractor has now approached URA and asked to submit a bid for the cost of producing another 20 guidance controls. Use Exhibit 6.4 and Exhibit 6.5.

  

    

     

What will be the average time for the 20 missile guidance controls? (Round your answer to the nearest whole number.)

    

   

What will the average cost be for guidance control for the 20 in the contract? (Round your answer to the nearest dollar amount.)

   

United Research Associates (URA) had received a contract to produce two units of a new cruise missile guidance control. The first unit took 5,000 hours to complete and cost $30,000 in materials and equipment usage. The second took 3,750 hours and cost $19,500 in materials and equipment usage. Labor cost is charged at $25 per hour.

     The prime contractor has now approached URA and asked to submit a bid for the cost of producing another 20 guidance controls. Use Exhibit 6.4 and Exhibit 6.5.

Explanation / Answer

Labor Hours

Cost per unit

1st unit

5000

$30,000

2nd unit

3750

$19,500

Learning %

3750/5000 = 0.75 = 75%

19500/30000 = 0.65 = 65%

a.

Labor hours required for Nth control = TN = T1*C

TN = number of labor-hours required to produce the Nth unit

T1 = number of labor-hours required to produce the first unit

C = learning-curve coefficient found in Exhibit 6.4 for Learning %

Labor hours required for 22nd control = T22

For 22nd unit at 75% learning curve, C = 0.2772

Labor hours required for 22nd control = T22 = 5000 x 0.2772

T22 = 1386 hours

Material and machine cost estimation for 22nd control = C22

For 22nd unit at 65% learning curve, C = 0.1465

Material and machine cost estimation for 22nd control = T22 = $30,000 x 0.1465

C22 = $4,395

Total Cost Required for 22nd control = $25 x T22 + C22

                                                     = $25 x 1368 + $4,395

                                                        = $38,595

Total Cost Required for last unit (22nd control) = $38,595

b.

What will be the average time for the 20 missile guidance controls?

Total time for building next 20 control = Total time required for 22 control – total time required for 2 control

Total time required for N control = TN = T1 x CT

TN = Total Time required to produce the N unit

T1 = number of labor-hours required to produce the first unit

CT = Cumulative learning-curve coefficient found in Exhibit 6.5 for Learning %

Total time required for 22 control = T22 = T1 x CT

For 22 units at 75% learning curve, CT = 9.388

T22 = T1 x CT = 4000 x 9.388 = 37,552 hours

Total time required for 2 control = T2 = T1 x CT

For 2 units at 75% learning curve, CT = 1.750

T22 = T1 x CT = 4000 x 1.750 = 7,000 hours

Total time for building next 20 control = T22 – T2 = 37552 – 7000 = 30552

Average time for the 20 missile guidance controls = 30,552/20 = 1527.6 hours

c.

What will the average cost be for guidance control for the 20 in the contract?

Total materials and machine cost estimation for N control = CN = C1 x CT

CN = materials and machine cost required to produce the N unit

T1 = materials and machine cost of producing the first unit

CT = Cumulative learning-curve coefficient found in Exhibit 6.5 for Learning %

Total materials and machine cost required for 22 controls = C22 = C1 x CT

For 22 units at 65% learning curve, CT = 6.492

T22 = T1 x CT = $30,000 x 6.492 = $194,760

Total materials and machine cost required for 2 controls = C2 = C1 x CT

For 2 units at 65% learning curve, CT = 1.650

C2 = C1 x CT = $30,000 x 1.750 = $49,500

Total materials and machine cost building next 20 control = C22 – C2 = $194,760 – $49,500 = $145,260

Average materials and machine cost for the 20 missile guidance controls = $145,260/20 = $7,263hours

Average cost be for guidance control for the 20 in the contract

= Average Labor Cost + Average materials and machine cost

= Average hours req. x Labor cost + $7,263

= 1527.6 x $25 + $7,263

= $45,453

Average cost be for guidance control for the 20 in the contract = $45,453

Labor Hours

Cost per unit

1st unit

5000

$30,000

2nd unit

3750

$19,500

Learning %

3750/5000 = 0.75 = 75%

19500/30000 = 0.65 = 65%

Dr Jack
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Chat Now And Get Quote