Utilize the project table detailed in months to optimize the project crash durat
ID: 464671 • Letter: U
Question
Utilize the project table detailed in months to optimize the project crash duration.Determine the normal project completion time frame. Find the maximum values for crashed project completion.Determine and provide for the total cost of each.
Activity
Predecessor
Duration: Crash Duration:
Cost: Crash Cost:
1
-
3 2
300 450
2
1
2 1
350 650
3
2
10 7
1,250 1,420
4
2
6 4
880 1,040
5
3
5 2
675 960
6
4,5
3 1
325 705
Activity
Predecessor
Duration: Crash Duration:
Cost: Crash Cost:
1
-
3 2
300 450
2
1
2 1
350 650
3
2
10 7
1,250 1,420
4
2
6 4
880 1,040
5
3
5 2
675 960
6
4,5
3 1
325 705
Explanation / Answer
The normal project completion time frame is 23 days .
The maximum value for crashed project completion is $ 5,225
The total cost for normal project completion is $ 3.780
===========================================================================
Activity Predecessor Normal duration Crash duration Normal cost Crash cost Early start Early finish 1 _ 3 2 300 450 0 3 2 1 2 1 350 650 3 5 3 2 10 7 1250 1420 5 15 4 3 6 4 880 1040 5 11 5 3 5 2 675 960 15 20 6 4,5 3 1 325 705 20 23Related Questions