1. The first step in the project development process is: A. customer future need

ID: 462844 • Letter: 1

Question

1. The first step in the project development process is: A. customer future needs projection B. product idea generation C. technology selection for product development D. technology development for process selection E. product marketing and distribution preparation

2. Which of the following Deming’s point encourages concurrent engineering? A) constantly improve the system B) create constancy of purpose C) institute education and self-improvement D) break down barriers between departments E) adopt a new philosophy

3. A theory that is generated by observation and description is said to have been developed by the process of: A. deduction B. abstraction C. speculation D. induction E. supposition

4. ) Services that we actively seek out and employ of our own accord are referred to as ________ services. A) internal B) voluntary C) do it yourself D) intangible E) personal

5. The elimination of waste results in: A. lower quality B. higher price C. higher productivity D. higher cost E. none of these are true

6. The __________ process involves identifying measures, establishing time frames for future data collection, gathering data, and analyzing data on an ongoing basis to identify performance trends and changes. A. conformance B. baselining C. reengineering D. cost control E. benchmarking

7. A particular customer requirement is associated with a technical requirement, has an importance of 5, a target value of 5, and a sales point value of 2. The absolute weight of this customer requirement is ________. A) 10 B) 20 C) 15 D) 50 E) 7

8. ________ is the term used to characterize the relationship between suppliers and customers when a high degree of linkages and interdependencies exist. A) Value partnering B) Customer co-production C) Supplier-customer interaction D) Supplier linkage E) Supplier alliance

9. ________ reduces the risk of supply interruption A) Constricted sourcing B) Selective sourcing C) Single sourcing D) Generic sourcing E) Dual sourcing

10. What is the first step for supplier development? A) Identify critical suppliers B) Identify key projects C) Define details of agreement D) Identify critical products and services E) Meet with supplier top management

Explanation / Answer

The first step in the project development process is product idea generation.

Which of the following Deming’s point encourages concurrent engineering? - constantly improve the system.

A theory that is generated by observation and description is said to have been developed by the process of abstraction.

Services that we actively seek out and employ of our own accord are referred to as voluntary services.

The elimination of waste results in higher productivity.

The reengineering process involves identifying measures, establishing time frames for future data collection, gathering data, and analyzing data on an ongoing basis to identify performance trends and changes.

A particular customer requirement is associated with a technical requirement, has an importance of 5, a target value of 5, and a sales point value of 2. The absolute weight of this customer requirement is 10.

Supplier alliance is the term used to characterize the relationship between suppliers and customers when a high degree of linkages and interdependencies exist.

Dual sourcing reduces the risk of supply interruption.

What is the first step for supplier development? - Identify critical suppliers