In the following MRP planning schedule for Item J, indicate the correct net requ
ID: 461633 • Letter: I
Question
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.)
Item J
Period 1 2 3 4 5 Gross Requirements 70 46 69Item J
Scheduled receipts LT = 1 Projected available balance Q=L4L Net requirememts Planned order receipts Planned order releases WEEK NUMBER ITEM J Gross requirements On-hand Net requirements Planned order receipt Planned order release 5 46 69 70 36Explanation / Answer
Period 0 1 2 3 4 5 Gross Requirements 0 70 0 46 69 Scheduled Receipts 0 0 0 0 0 Projected on Hand 36 36 36 0 0 0 Net Requirements 0 34 0 46 69 Planned Order Receipts 0 34 0 46 69 Planned Order Releases 34 0 46 69 0
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.