Question
A work center has five jobs assigned to it. They are labeled, in the order of their arrival in the shop, as jobs A, B, C, D, and E. The work center may work on only one job at a time and must complete any job it starts before starting another job. Job A has a processing time of 6 days and is due to the customer in 9 days. Job B has a processing time of 2 days and is due in 16 days. Job C has a processing time of 4 days and is due in 10 days. Job D has a processing time of 3 days and is due in 7 days. Job E has a processing time of 5 days and is due in 12 days. Using the shortest operating time priority rule, in what order should these jobs be undertaken?
Explanation / Answer
Below is the sequence
Job PROCESSING TIME DUE FLOW TIME DAYS LATE B 2 16 2 0 D 3 7 5 0 C 4 10 9 0 E 5 12 14 2 A 6 9 20 11Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.