Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Which of the following statements will be TRUE of the critical path for a projec

ID: 443763 • Letter: W

Question

Which of the following statements will be TRUE of the critical path for a project that has one and only one critical path?

a. Reducing the duration of an activity on this path by one day will reduce the duration of the project by one day.

b. Reducing the duration of an activity on this path by two days will reduce the duration of the project by two days. c. It is possible for an activity on this path to have slack time, if that activity is also on “non-critical” paths.

d. All of the these answers will always be true e. None of these answers will always be true

Explanation / Answer

(a) Reducing the duration of an activity on this path by one day will reduce the duration of the project by one day will be TRUE of the critical path for a project that has one and only one critical path.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote