You have a project to build a new block wall. The block wall is four sided with
ID: 443610 • Letter: Y
Question
You have a project to build a new block wall. The block wall is four sided with all sides being equal. Each side is to take one day to build and is budgeted for $10,000 per side. The sides are planned to be completed one after the other. Regarding project financial management, specifically revenues and cash flows: You will be paid for each side as that side is completed and accepted. In this case, assume that the sides have a finish-to-finish relationship instead of a finish-to-start relationship so more than one side can be worked on at the same time (in parallel).
Explanation / Answer
Hi Dear,
More than one side can be made at a time. Construction of walls can be done with parallel or two lengths and two withs at a time. The project is finish to finish not finish to satart. Once one side or two sides are complete then other wor can be considered.
Regards,
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.