You have a project to build a new block wall. The block wall is four sided with

ID: 443610 • Letter: Y

Question

You have a project to build a new block wall. The block wall is four sided with all sides being equal. Each side is to take one day to build and is budgeted for $10,000 per side. The sides are planned to be completed one after the other. Regarding project financial management, specifically revenues and cash flows: You will be paid for each side as that side is completed and accepted. In this case, assume that the sides have a finish-to-finish relationship instead of a finish-to-start relationship so more than one side can be worked on at the same time (in parallel).

Explanation / Answer

Hi Dear,

More than one side can be made at a time. Construction of walls can be done with parallel or two lengths and two withs at a time. The project is finish to finish not finish to satart. Once one side or two sides are complete then other wor can be considered.

Regards,

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote