Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

3. Compute the early, late, and slack times for the activities in the network th

ID: 443080 • Letter: 3

Question

3. Compute the early, late, and slack times for the activities in the network that

follows, assuming a time-constrained network. Which activities are critical?

What is the time-constrained project duration?

Note: Recall, in the schedule resource load chart the time-constrained scheduling

interval (ES through LF) has been shaded. Any resource scheduled beyond

the shaded area will delay the project.

Assume you have only three resources and you are using a computer that

uses software that schedules projects by the parallel method and following heuristics.

Schedule only one period at a time!

Minimum slack

Smallest duration

Lowest identification number

Keep a log of each activity change and update you make each period—e.g.,

period 0–1, 1–2, 2–3, etc. (Use a format similar to the one on page 261.) The log

should include any changes or updates in ES and slack times each period,

activities scheduled, and activities delayed. (Hint: Remember to maintain the

technical dependencies of the network.) Use the resource load chart to assist

you in scheduling (see pages 262–263—Figures 8.4 and 8.5).

List the order in which you scheduled the activities of the project. Which

activities of your schedule are now critical?

Recompute your slack for each activity given your new schedule. What is the

slack for activity 1? 4? 5?

Explanation / Answer

1) Early Start =   ES+  t

=0+2

=2

2)1+1 = 2

3)2+1=3

4)0+1=1

5)1+2=3

6)1+2=3

LF  = LF - t

LF= Latest Finish time

1)2-1=1

2)2-1=1

3)0-1=-1

4)2-1=1

5)2-2=0

6)0-2=-2

_______________________________________________________________________________________

Slack =  LF - EF

1) 1 - 2

=-1

2)1-2=-1

3)-1 - (-1)=+2

4) 1+1 =2

5)0+3=3

6) -2 +3=   - 1

______________________________________________________________________________________

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote