You are the new process manager at a local manufacturer, and your first job is to inspect the quality of the end products. You conducted a 5-day data collection study to assess the quality of the products, and each day, you inspected 3,000 bottles. The company can produce a maximum of 450,000 bottles per day. The results are as follows Sample Day 1 Day 2 Day 3 Day 4 Day 5 # defected 80 120 201 155 102 Sample Size 3000 3000 3000 3000 3000 What are values of p-bar, Sp, UCL and LCL based on the results above.? Please use a confidence interval of 3 standard deviationsExplanation / Answer
p-bar = total no. of defects/total no. of observations
= (80+120+201+155+102)/(5*3000)
= 0.0439
Sp = standard deviation of pbar = [(p*(1-p))/n]^0.5
= [0.0439*(1-0.0439)/3000]^0.5
= 0.003739
UCL = p-bar+z*Sp
= 0.0439+3*0.003739
= 0.0551
LCL = p-bar - z*Sp
= 0.0439-3*0.003739
= 0.0326
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.