Lady Bug Machineries uses a lean production assembly line to make its generators
ID: 432842 • Letter: L
Question
Lady Bug Machineries uses a lean production assembly line to make its generators. In one assembly area, the demand is 200 parts per 8-hour day. It uses a container that holds 10 parts. It typically takes about 5 hours to round-trip a container from one work center to the next and back again. They also desire to hold a 20% safety stock of this part in the system.
If the container size were 15 and there were 10 containers, what would be the new required round-trip time, all else being constant?
Explanation / Answer
Answer:
Note: Please rate the answer.
Explanation:
Initially:
When Container size is increased to 15 and 10 container: