Given a simple Project like the one pictured above. Optimistic / Most Likely / P
ID: 431893 • Letter: G
Question
Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations were calculated. For Path 1-2-5 we have a Path Mean = 32 and a Path Standard Deviation = 5. For Path 1-3-4-5 we have a Path Mean = 29 and a Path Standard Deviation = 2. Determine both the Probability that Path 1-2-5 will finish in 32 Days or Less and the Probability that the Project will finish in 32 Days or Less.
Question 3 options:
0.977249938 : 0.977249938
0.5 : 0.466596385
0.788144666 : 0.787961286
0.884930268 : 0.884927259
Save
1-0.977249938 : 0.977249938
2-0.5 : 0.466596385
3-0.788144666 : 0.787961286
4-0.884930268 : 0.884927259
Explanation / Answer
Path 1-2-5
Mean = 32, SD = 5
Prob (Complete <= 32) = NORMDIST(32, Mean, SD, TRUE) = NORMDIST(32, 32, 5, TRUE) = 0.50
Path 1-3-4-5
Mean = 29, SD = 2
Prob (Complete <= 32) = NORMDIST(32, 29, 2, TRUE) = 0.933193
Entire project
Prob (Entire Project completes by 32 days) = Prob (1-2-5 completes by 32 days) AND Prob (1-3-4-5 completes by 32 days)
= 0.50 x 0.933193 = 0.466596
So, option 2 is correct.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.