Multiple Choice: Select Best Single Answer. Which of the following best describe
ID: 431879 • Letter: M
Question
Multiple Choice: Select Best Single Answer.Which of the following best describes the project manager's role as an integrator? a. Get all team members together into a cohesive whole b. Put all the pieces of a project into a program c. Put all the pieces of a project into a cohesive whole d. Help team members become familiar with a project 7. A project manager is in the process of validating the scope of a deliverable with the customer. is the MOST important thing the project manager should ensure? Accuracy of the deliverable a. b. Timeliness of the deliverable Acceptance of the deliverable c. d. Completeness of the deliverable 8. Which of the following is not true about the WBS? a. It decomposes work into discrete units b. Each work package is associated with only one control account c. The WBS is usually represented in a hierarchical fashion d. It should be used only for large, long-term projects
Explanation / Answer
Answer: 6: Option: C: Put all the pieces of a project into a cohesive whole
Integration means to combine all the activities and manage by the manager. Integration is very necessary for project success. No project can be run without integration.
Answer: 7: Option C: Acceptance of the deliverable.
Validate scope is the process of formalizing the acceptance of the completed project deliverables. All the team members of the project is working on the project to complete it before deadline. Once it has been completed than they must be reviewed by the customer to check whether they meet with their requirements or not. A deliverables is accepted and mark as completed only if it is accepted by the customer.
Answer: 8: D Option: It should be used only for large, long term projects.
WBS is also used for small and short term projects as well because with the help of WBS the project is divided into small units and forces the team to create detailed step of the project. It helps to project manager to assigning responsibilities, resource allocation, monitoring the project and controlling the project.