Multiple Choice: Select Best Single Answer. 4. Which of the following statements
ID: 431878 • Letter: M
Question
Multiple Choice: Select Best Single Answer. 4. Which of the following statements is not true? a. The project charter formally authorizes the project b. The project scope management plan is separate from the project management plan. c. The project scope statement describes project deliverables and constraints. d. The project scope statement provides a common understanding of the project scope among project stakeholders 5. Which of the following statements about project life cycles is not true? a. A curve depicting a typical project life cycle will peak during the project execution A typical project life cycle will have a slow beginning in comparison to other Changes cost more early in a project life cycle because plans will have to be remade Risk is greatest at the beginning of a project life cycle. stage. stages to accommodate the changes. b. c. d.Explanation / Answer
4. Project scope management plan is similar to the project management plan. Hence, Statement b is False.
Answer: Option b
5. In a project life cycle, the earlier a change is identified, the cheaper is its incorporation and implementation.
Hence, Statement c is False.
Answer: Option c