1. risks can be identified by using all the following except: A. Historical info
ID: 430194 • Letter: 1
Question
1. risks can be identified by using all the following except:A. Historical information B. Previously identified risks. C. Ignoring potential problems. D. Progressive elaboration
2. ___ involves the following. Analyzing cost performance to determine which work packages may require corrective actions, deciding what specific coreective action should be taken, and revising the project plan- including time and it's estimates- to incorporate the planned corrective action
A. Resource analysis B. Problem solving C. CPI monitoring D. Cost control.
1. risks can be identified by using all the following except:
A. Historical information B. Previously identified risks. C. Ignoring potential problems. D. Progressive elaboration
2. ___ involves the following. Analyzing cost performance to determine which work packages may require corrective actions, deciding what specific coreective action should be taken, and revising the project plan- including time and it's estimates- to incorporate the planned corrective action
A. Resource analysis B. Problem solving C. CPI monitoring D. Cost control.
1. risks can be identified by using all the following except:
A. Historical information B. Previously identified risks. C. Ignoring potential problems. D. Progressive elaboration
2. ___ involves the following. Analyzing cost performance to determine which work packages may require corrective actions, deciding what specific coreective action should be taken, and revising the project plan- including time and it's estimates- to incorporate the planned corrective action
A. Resource analysis B. Problem solving C. CPI monitoring D. Cost control.
Explanation / Answer
Q- 1 a)Ignoring potential problems Q- 2 D) Cost control