2. Process times for all jobs are one hour. Changeovers between families require

ID: 424009 • Letter: 2

Question

2. Process times for all jobs are one hour. Changeovers between families require four hours. Thus, the completion time for job 1 is 5, for job 2 is 6, for job 3 is 11, and so on. Job Number Family CodeDue Date 6 12 13 15 19 20 4 6 25 27 10 a) How many possible sequences are there? b) Compute the total tardiness of the current sequence (i.e. 1 to 10). c) Is there any sequence with no tardiness? d) Here, the processing times are deterministic (one hour). Suppose you are dealing with uniformly distributed stochastic processing times (e.g. 45 t

Explanation / Answer

Job 1 2 3 4 5

Processing time 1 1 1 1 1

Due date 5 6 7 8 9

Flow time 1 2 8 9 10

Tardiness 0 0 1 1 1

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote