Final Exam Spring A one year project was budgeted at $1,000,000. Meanwhile, and
ID: 421892 • Letter: F
Question
Final Exam Spring A one year project was budgeted at $1,000,000. Meanwhile, and after exactly seven months fron start of the project execution, the following current figures have been assessed: PV: $500,000 EV: $450,000 AC: $550,000. 37. What estimate at comple tion can you derive from these figures? a) $1,000,000 b) $1,222,222 c) $1,550,000 d) $550,000 e) None of the above 38. What is the needed time (from now) to complete the project? a) 1.3 months b) 13.3 months c) 6.3 months d) 1 year e) None of the above 39. How is the project is doing based on time (schedule)? a) Project is ahead of schedule b) Project is behind schedule c) Project is over budget d) Project is on schedule e) I cannot estimate based on the information provided 40. How is the project is doing based on cost (budget)? a) Project is ahead of schedule b) Project is under budget c) Project is over budget d) Project is on budget e) I cannot estimate based on the information provided Answer the following question on the following sheet (5 point A Project Manager is performing critical path analysis. The activities, their duration in d Slrotoh tha network diagram: show on theExplanation / Answer
37.
B
Working note:
EAC = BAC/CPI = 1000000/(450000/550000) = $1222222
38.
C
Working note:
SPI = EV/PV = 450000/500000 = .9
Estimated Time to complete = 12/.9 = 13.33 months
So, expected time to complete = 13.33 – 7 = 6.33 month
39.
B
Project is behind the schedule, as it is expected to take 13.33 months against the original time of 12 months.
40.
C
Project is over budget, because it requires $1222222 in comparison to the BAC of $1000000 only.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.