Project Monitoring Controlling 1) Match the questions in the left column to the

ID: 418549 • Letter: P

Question

Project Monitoring Controlling

1) Match the questions in the left column to the terms in the right column.

What is the revised estimate for the final cost at the completion of the project?

PV

How much money was expended thus far?

EV

How much physical work was actually accomplished thus far?

AC

How much money was originally budgeted?

BAC

From where we are today, how much money is needed to complete the work?

SV

By how much have we deviated from the schedule baseline, favourably or unfavourably?

CV

By how much have we deviated from the cost baseline, favourably or unfavourably?

EAC

What is the planned cost or value of the work accomplished thus far?

ETC

What is the revised estimate for the final cost at the completion of the project?

PV

How much money was expended thus far?

EV

How much physical work was actually accomplished thus far?

AC

How much money was originally budgeted?

BAC

From where we are today, how much money is needed to complete the work?

SV

By how much have we deviated from the schedule baseline, favourably or unfavourably?

CV

By how much have we deviated from the cost baseline, favourably or unfavourably?

EAC

What is the planned cost or value of the work accomplished thus far?

ETC

Explanation / Answer

What is the revised estimate for the final cost at the completion of the project?

ETC

How much money was expended thus far?

AC

How much physical work was actually accomplished thus far?

EV

How much money was originally budgeted?

BAC

From where we are today, how much money is needed to complete the work?

EAC

By how much have we deviated from the schedule baseline, favourably or unfavourably?

SV

By how much have we deviated from the cost baseline, favourably or unfavourably?

CV

What is the planned cost or value of the work accomplished thus far?

PV

What is the revised estimate for the final cost at the completion of the project?

ETC

How much money was expended thus far?

AC

How much physical work was actually accomplished thus far?

EV

How much money was originally budgeted?

BAC

From where we are today, how much money is needed to complete the work?

EAC

By how much have we deviated from the schedule baseline, favourably or unfavourably?

SV

By how much have we deviated from the cost baseline, favourably or unfavourably?

CV

What is the planned cost or value of the work accomplished thus far?

PV