Project Monitoring and Control Process Plan: You have a Project Budget for build

ID: 328301 • Letter: P

Question

Project Monitoring and Control Process Plan:
You have a Project Budget for building a five-bedroom house in Ashburn, VA. Assume that your building project is two months behind and has a $100,000.00 cost overrun. This should not be a surprise to you because of the monitoring processes. Identify and discuss some of the monitoring processes that could have alerted you of the schedule and cost problems. What are some of the controlling steps you would take to bring both the schedule and the cost back on track? Be sure to justify your answers. . Your Project Monitoring and Control Process Plan should be at least two pages including a summarization and conclusion page. If necessary, include data from the Project Budget and Project Schedule in the table shown below to support your schedule and cost problems.

Unit 5 Project: Activity Description Start Date End Date Days to complete Est $ Architectural Design 5/1/2018 5/15/2018 14 50,000 Procurement of machinery 5/15/2018 5/30/2018 15 60,000 Hiring Labor 5/31/2018 6/10/2018 10 120,000 Work and Environmental Permits 7/27/2018 8/6/2018 10 25,000 Site Security 8/18/2018 4/30/2020 731 20,000 Concrete 8/18/2018 8/31/2018 15 80,000 Lumber Procurement 9/1/2018 9/11/2018 10 80,000 Material Storage 9/1/2018 4/30/2020 637 10,000 Scaffolding Erection 9/12/2018 9/17/2018 5 25,000 Framing 9/15/2018 1/13/2019 120 130,000 Roofing 1/14/2019 2/13/2019 30 40,000 Plumbing 2/14/2019 3/17/2019 30 30,000 Electrical 3/18/2019 4/17/2019 30 30,000 HVAC 4/18/2019 6/2/2019 45 40,000 Windows and Doors 6/3/2019 8/2/2019 60 20,000 Drywall 8/3/2019 9/12/2019 40 45,000 Interior Design 9/13/2019 10/23/2019 40 15,000 Paint and Wood Finishing 10/24/2019 12/23/2019 60 40,000 Cabinetry 12/24/2019 1/8/2020 15 40,000 Plumbing Fixtures 12/24/2019 1/8/2020 15 20,000 Lighting Fixtures 12/24/2019 1/8/2020 15 20,000 Flooring 1/9/2020 1/30/2020 21 30,000 Interior Decorator and Decorations 1/31/2020 2/20/2020 20 20,000 Exterior Rock 2/21/2020 3/22/2020 30 50,000 Landscaping 3/23/2020 4/15/2020 23 30,000 Cost of Construction 1,040,000 Contingency (2%) 4/16/2020 4/30/2020 14 19,800 Total 1,059,800

Explanation / Answer

The major concern at the inception of any project is timely completion within the budgetary allocation. This is however, impossible to achieve without constant monitoring and timely action against deviations if any. The importance of this was recognised by organisations which have project based activities and gave birth to a different organisational structure based on projects. A well prepared project monitoring and control process plan can go a long way in the final outcome and ensure the success of the project.

The monitoring plan is synonymous with the project plan itself and needs to work in close synchronicity with the project activities at each step. It needs to identify the project activity, the resources available, the steps involved and identification of risks involved. Next step would be to measure the progress of activity as per schedule and identify deviations if any in terms of time taken or resources allocated or any external factors which may impact timely completion of project or budgets. Once the deviations are identified there is a need to evaluate the causes for the deviations and then put in immediate control measures to minimize negative impact on project cost and completion. Corrective measures need to be speedily implemented and involve quick decision making as to how and where controls need to be implemented to be most effective. This may entail taking remedial action or at times the plan itself may have certain unrealistic targets and then the plan may itself need to be revised or simply amended for certain tasks. The trine of a realistic project plan, an effective step by step monitoring system to identify deviations earliest and a quick and decisive control process can guarantee completion of a project successfully.

The project monitoring and control samples are listed in the table below :

Unit 5 Project:

P=project plan

D= Deviation

Activity Description

Start Date

End Date

Days to complete

Est $   

Project monitoring

Control Process

Architectural Design

5/1/2018

5/15/2018

14

50,000

Designing as required and does not require P changes

If any D in cost or design modify allocations

Procurement of machinery

5/15/2018

5/30/2018

15

60,000

Ensure cost and setup as per P report D

Verify sourcing is the most viable else try to reduce cost to create buffer

Hiring Labor

5/31/2018

6/10/2018

10

120,000

Ensure as required and daily desired output can be achieved

If any D identify cause and explore more viable sourcing Consider overlapping activity 2,3,4 to create an additional 10 day buffer time

Work and Environmental Permits

7/27/2018

8/6/2018

10

25,000

Ensure all required permits are obtained

Verify changes in policies which may be advantageous

Site Security

8/18/2018

4/30/2020

731

20,000

Ensure cross check to secure site no loopholes

Ensure audit of security measures employed/deployed

Concrete

8/18/2018

8/31/2018

15

80,000

Best sourcing and quality required standards D if any

D to be controlled by ensuring right quality and mix at best price change if needed

Lumber Procurement

9/1/2018

9/11/2018

10

80,000

ditto

ditto

Material Storage

9/1/2018

4/30/2020

637

10,000

Should be secure and checks and surveillance installed any excess outflow can be verified here on daily basis

Ensure P D are checked and identify changes in material requirements identify control measures cuts or rebudget

Scaffolding Erection

9/12/2018

9/17/2018

5

25,000

Ensure as per design

And no D from required strength and on time

Ditto

Framing

9/15/2018

1/13/2019

120

130,000

Ditto

Ditto

Roofing

1/14/2019

2/13/2019

30

40,000

Ditto

Ditto

Plumbing

2/14/2019

3/17/2019

30

30,000

Ditto

Ditto

Electrical

3/18/2019

4/17/2019

30

30,000

Ditto

Ditto

HVAC

4/18/2019

6/2/2019

45

40,000

Ditto

Ditto

Windows and Doors

6/3/2019

8/2/2019

60

20,000

Ditto

Ditto

Drywall

8/3/2019

9/12/2019

40

45,000

Ditto

Ditto

Interior Design

9/13/2019

10/23/2019

40

15,000

Ditto

Ditto

Paint and Wood Finishing

10/24/2019

12/23/2019

60

40,000

Ditto

Ditto

Cabinetry

12/24/2019

1/8/2020

15

40,000

Ditto

Ditto

Plumbing Fixtures

12/24/2019

1/8/2020

15

20,000

Ditto

Ditto

Lighting Fixtures

12/24/2019

1/8/2020

15

20,000

Ditto

Ditto

Flooring

1/9/2020

1/30/2020

21

30,000

Ditto

Ditto

Interior Decorator and Decorations

1/31/2020

2/20/2020

20

20,000

Ditto

Ditto

Exterior Rock

2/21/2020

3/22/2020

30

50,000

Ditto

Ditto

Landscaping

3/23/2020

4/15/2020

23

30,000

Ditto

Ditto

Cost of Construction

1,040,000

Contingency (2%)

4/16/2020

4/30/2020

14

19,800

Increase to 4% if possible by above measures

Ensure D control is quick and contingency requirement is not beyond 2%

Total

1,059,800

If a project is monitored at every step and activity it facilitates close monitoring to identify deviations immediately and control resultant damage through implementation of corrective measures at the earliest.

Unit 5 Project:

P=project plan

D= Deviation

Activity Description

Start Date

End Date

Days to complete

Est $   

Project monitoring

Control Process

Architectural Design

5/1/2018

5/15/2018

14

50,000

Designing as required and does not require P changes

If any D in cost or design modify allocations

Procurement of machinery

5/15/2018

5/30/2018

15

60,000

Ensure cost and setup as per P report D

Verify sourcing is the most viable else try to reduce cost to create buffer

Hiring Labor

5/31/2018

6/10/2018

10

120,000

Ensure as required and daily desired output can be achieved

If any D identify cause and explore more viable sourcing Consider overlapping activity 2,3,4 to create an additional 10 day buffer time

Work and Environmental Permits

7/27/2018

8/6/2018

10

25,000

Ensure all required permits are obtained

Verify changes in policies which may be advantageous

Site Security

8/18/2018

4/30/2020

731

20,000

Ensure cross check to secure site no loopholes

Ensure audit of security measures employed/deployed

Concrete

8/18/2018

8/31/2018

15

80,000

Best sourcing and quality required standards D if any

D to be controlled by ensuring right quality and mix at best price change if needed

Lumber Procurement

9/1/2018

9/11/2018

10

80,000

ditto

ditto

Material Storage

9/1/2018

4/30/2020

637

10,000

Should be secure and checks and surveillance installed any excess outflow can be verified here on daily basis

Ensure P D are checked and identify changes in material requirements identify control measures cuts or rebudget

Scaffolding Erection

9/12/2018

9/17/2018

5

25,000

Ensure as per design

And no D from required strength and on time

Ditto

Framing

9/15/2018

1/13/2019

120

130,000

Ditto

Ditto

Roofing

1/14/2019

2/13/2019

30

40,000

Ditto

Ditto

Plumbing

2/14/2019

3/17/2019

30

30,000

Ditto

Ditto

Electrical

3/18/2019

4/17/2019

30

30,000

Ditto

Ditto

HVAC

4/18/2019

6/2/2019

45

40,000

Ditto

Ditto

Windows and Doors

6/3/2019

8/2/2019

60

20,000

Ditto

Ditto

Drywall

8/3/2019

9/12/2019

40

45,000

Ditto

Ditto

Interior Design

9/13/2019

10/23/2019

40

15,000

Ditto

Ditto

Paint and Wood Finishing

10/24/2019

12/23/2019

60

40,000

Ditto

Ditto

Cabinetry

12/24/2019

1/8/2020

15

40,000

Ditto

Ditto

Plumbing Fixtures

12/24/2019

1/8/2020

15

20,000

Ditto

Ditto

Lighting Fixtures

12/24/2019

1/8/2020

15

20,000

Ditto

Ditto

Flooring

1/9/2020

1/30/2020

21

30,000

Ditto

Ditto

Interior Decorator and Decorations

1/31/2020

2/20/2020

20

20,000

Ditto

Ditto

Exterior Rock

2/21/2020

3/22/2020

30

50,000

Ditto

Ditto

Landscaping

3/23/2020

4/15/2020

23

30,000

Ditto

Ditto

Cost of Construction

1,040,000

Contingency (2%)

4/16/2020

4/30/2020

14

19,800

Increase to 4% if possible by above measures

Ensure D control is quick and contingency requirement is not beyond 2%

Total

1,059,800