Question
cure https://newconnectmheducation.com/flow/connect.html Saved Help Save How are the wBS and project networks linked? (You may select more than one answer. Single click question mark to produce a check mark for a correct answer and double click the box with the que empty the box for a wrong answer) Time estimates required for a work package in the WBS are set in time frames, but without dates 2 The time estimates found in the work packages of the WBS are used to develop the network The dates are computed before the network is developed besed on time frames from the WBS ? Resources required for a work package in the WBS are set in time frames, with datesExplanation / Answer
How are the wbs and project network linked .