4.3. Using the following product tree, determine the planned order receipts and
ID: 414721 • Letter: 4
Question
4.3. Using the following product tree, determine the planned order receipts and planned are 1 weelk order releases if 200 As are to be produced in week 5. All lead times order releases if 2 except for component E, which has a lead time of 2 weeks. 4 Week Part A Lead Time: 1 weekPlanned Order Release Part B Lead Time: 1 week Planned Order Release Part C Lead Time: 1 week Planned Order Release Part D Lead Time: 1 week Planned Order Release Part E Lead Time: 2 weeks Planned Order Release Planned Order Receipt Planned Order Receipt Planned Order Receipt Planned Order Receipt Planned Order ReceiptExplanation / Answer
Order Quantity: 200 A's Delivery date: 31/03/2018 Buffer time: 1 day in each planned/receipt to consider unexpected delay 1 2 3 4 5 Part A Planned order receipt 26/02/2018 30/03/2018 Lead Time: 1 week Planned order release 07/04/2018 Part B Planned order receipt 22/03/2018 Lead Time: 1 week Planned order release 14/03/2018 Part C Planned order receipt 22/03/2018 Lead Time: 1 week Planned order release 14/03/2018 Part D Planned order receipt 13/03/2018 Lead Time: 1 week Planned order release 05/03/2018 Part E Planned order receipt 13/03/2018 Lead Time: 2 weeks Planned order release 27/02/2018
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.