Brian is assigned his first project. If things go well, he should get promoted.
ID: 408120 • Letter: B
Question
Brian is assigned his first project. If things go well, he should get promoted. The CEO is aware of this project, so he has a chance for high visibility. His first task is to define the work break down structure by interviewing project activity managers, and the firm's friendly, yet boring accountants, to get "good estimates" of project activity times and costs. For Activity Z, the crash cost per week is _____, given the following data: normal time = 5 weeks, crash time = 2, normal cost = $7,560, and crash cost = $17,365. Select one:
a. less than or equal to $1,000 per week
b. more than $1,000 but less than or equal to $2,500
c. more than $2,500 but less than or equal to $3,000
d. more than $3,000 but less than or equal to $3,500
Explanation / Answer
d. more than $3,000 but less than or equal to $3,500
Crash cost per week=(crash cost-normal cost)/(Normal duration-crash duration)
=(17365-7560)/(5-2)=3268.33
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.