You own a semipro baseball team (in the location of your choice) and you want to construct a new practice field. You own the land already (20 acres). The land is relatively flat and it has only a few dilapidated structures (barns) and trees on it. Connecting up with existing water and sewer lines would present no unusual technical problems. It is now September, and you would love to have that field ready to go by March 2 years hence. Your vision would include the playing field, a small clubhouse, and a parking area that would hold about 50 cars. No spectator seating would be required.
PROPOSAL
1. Breakdown of Bid Price
2. Revisions and Extra Work
3. Escalation Formulas
4. Scheduled Completion Dates
5. List of Subcontractors
Explanation / Answer
price breakdown :
civil works:
leveling of field: 20000 for 5 days , ( 5 in the end)
excavation : 10 days - 25000
basement : 15 days - 100000
structure- 300 days- 2000000
Electrical wirings: - 20 days- 25000
dressing room, visitors room, spectator chairs and office room set ups: 15 days - 50000
pavement for parking: 50000 - 20 days
painting: 30 days - 100000
2. revisions and extra work : there are no revisions
3. no escalation
4. basement : by december
construction : 2 nd year october
electrical works: 2 nd year december
parking lot: 2 nd year january
rooms and chairs and boards : by 2 nyd year feb.
5. sub contractors :
EDP constructions
XSE Electricals
ERIC chairs and boards
MSE Lawn movers and levelers
SGX paints